ADP# 270

ESTABLISHMENT OF TAX FACILITATION CENTERS IN 06 DISTRICTS OF KHYBER PAKHTUNKHWA

Date of Approved PC-128.01.2015
Approved Cost 407.00  Million
Date of Completion: June-2021
Revised Cost Estimate: 
Date of Completion
Forum of Approval: PDWP
Total Duration—-


PROJECT DESCRIPTION
The project was approved by PDWP dated 28.01.2015 with a cost of Rs. 407.00 Million. TFC D.I.Khan has been completed, ETO office Sifted. Whereas the work on TFC Peshawar and TFC Nowshera is in progress. Total allocation for the CFY 2019-20 was 40.00 million out of which 10.00 million was released in first quarter out of this release 5.00 million was released to TFC Peshawar while 5.00 million was released to TFC Nowshera. Now 30 million has been released on 30.12.2019 by the Finance Department. The Finance Department has been requested to transfer/placement of funds amounting to Rs. 15 (M) for TFC Peshawar& 15 (M) for TFC Nowshera at the disposal of Secretary C&W vide this Department on date 07/01/2020.