ADP# 276

STRENGTHENING OF EXCISE TAXATION & NARCOTICS CONTROL DEPARTMENT

Date of Approved PC-1  24.09.2019
Approved Cost  65.347  Million
Date of Completion:  June-2021
Revised Cost Estimate: 
Date of Completion
Forum of Approval: DDWP
Total Duration 24 Months


PROJECT DESCRIPTION:
The project was approved by DDWP dated 24.09.2019 with a cost of Rs. 65.347 Million for a period of 24 months. Approved in the DDWP on 24-09-2019.Administrative Approval as per Concurrence of Finance Department issued for Rs.65.347 (M) on Dated.28/10/2019.The procurement work for machinery & equipment is in Progress. A letter has been sent to KPPRA to upload the tender notice on its website. Bid opening date is 11.02.2020 at DG ET&NC Office.