ADP# 415

STRENGTHENING/CAPACITY BUILDING OF NEW NARCOTICS CONTROL WING OF EXCISE, TAXATION & NARCOTICS CONTROL DEPARTMENT IN TRIBAL DISTRICTS

Date of Approved PC-1  15.11.2019
Approved Cost  27.80  Million
Date of Completion:  June-2021
Revised Cost Estimate: 
Date of Completion
Forum of Approval: DDWP
Total Duration 24 Months

 

PROJECT DESCRIPTION:
The project was approved by DDWP dated 15.11.2019 with a cost of Rs. 27.80 Million for a period of 24 months. Approved in the DDWP on 15-11-2019. Administrative Approval as per Concurrence of Finance Department NMA’s has been issued for Rs.27.80 (M) on Dated.10/12/2019. Funds not yet released by the Finance Department NMA’s.