ADP# 273
ESTABLISHMENT OF MODEL WAREHOUSE WITH ALLIED FACILITIES
Date of Approved PC-1 | 22-10-2020 |
Approved Cost | 265.00 Million (Estimated cost) |
Date of Completion: | — |
Revised Cost Estimate: | — |
Date of Completion | — |
Forum of Approval: | PDWP |
Total Duration | — |
PROJECT DESCRIPTION:
The Project was approved by PDWP dated 22-10-2020 with a cost of Rs. 265 Million. The payment of Rs. 4.6 Million has been made to M/S Allied Consultants for design consultancy. The work order has been issued to Contractor on 12-4-2021, but work on scheme could not be started on scheme till date due to existence of encroachments issues.