ADP# 276

STRENGTHENING OF EXCISE TAXATION & NARCOTICS CONTROL DEPARTMENT

Date of Approved PC-1   24.09.2019
Approved Cost   65.347  Million
Date of Completion:   June-2021
Revised Cost Estimate: 
Date of Completion
Forum of Approval:  DDWP
Total Duration  24 Months


PROJECT DESCRIPTION:

The project was approved by DDWP dated 24.09.2019 with a cost of Rs. 65.347 Million for a period of 24 months. Administrative Approval as per

Concurrence of Finance Department issued for Rs.65.347 (M) on Dated.28/10/2019.The procurement work for machinery & equipment is in Progress. The Project is extended till June, 2022.

  1. Procurement of hardware amounting to Rs. 8.356 million already done.
  2. Further procurement is in progress.
  • Hiring, training and other components will be resumed on release of further funds.

Funds are issued to tune of Rs. 25.00 Million during CFY 2021-22. An expenditure of Rs. 1.922 Million are made in scheme till date.